Proposed Projects

  • Preventive maintenance will be performed on the water tank at the Pepperhill Plant during the Spring Break, March 15-19,2021. There will be no break in the water supply to customers during the maintenance.
    03/19/2021
  • Pipeline Construction
    Second Half of 2023

    Reroute pipe covered by the Keenan Overpass.  Install a bore under Keenan Cutoff running from south to north and lay line down Adoue Road.

  • New Construction at 2 Plants
    2025-2026

    Add a 2nd storage tank and pressure pump at the Pepperhill and Staley Plants.

  • Security Upgrade
    Second half of 2023

    Add security cameras at the Staley Plant.

  • Replace Pipelines in 177
    In budget planning stage

    Replace pipeline beginning with Pine Point.

  • Pipeline Upgrades Outside 177 Lake Estates
    In budget planning stage

    This upgrade is in the budgeting stage.  Exact streets to be determined.

  • Construction of an Additional Plant
    2025-2026

    Search has begun to obtain land to construct a third well and plant.

  • Increase in Water Rates
    September 1, 2023

    Increase in water usage rates to be effective September 1, 2023.