Preventive maintenance will be performed on the water tank at the Pepperhill Plant during the Spring Break, March 15-19,2021. There will be no break in the water supply to customers during the maintenance.
03/19/2021
-
Pipeline Construction
Second Half of 2023
Reroute pipe covered by the Keenan Overpass. Install a bore under Keenan Cutoff running from south to north and lay line down Adoue Road.
-
New Construction at 2 Plants
2025-2026
Add a 2nd storage tank and pressure pump at the Pepperhill and Staley Plants.
-
Security Upgrade
Second half of 2023
Add security cameras at the Staley Plant.
-
Replace Pipelines in 177
In budget planning stage
Replace pipeline beginning with Pine Point.
-
Pipeline Upgrades Outside 177 Lake Estates
In budget planning stage
This upgrade is in the budgeting stage. Exact streets to be determined.
-
Construction of an Additional Plant
2025-2026
Search has begun to obtain land to construct a third well and plant.
-
Increase in Water Rates
September 1, 2023
Increase in water usage rates to be effective September 1, 2023.
-
Garbage Rate Increase
June 2023
Garbage rate will increase in June 2023.